Upcoming Construction Timeline

The following is a tentative schedule of projects at Park District facilities and parks. Projects are subject to change.

September 2024

Project includes:

    • Diving well removal
    • Installation of slides, lily pad crossing, and current channel

Anticipated completion: June 2025

March 2025

Project includes:

    • Geothermal well installation

Anticipated completion: May 2025

April 2025

Project includes:

    • Playground renovation
    • Shade structures
    • Entrance moving to northwest corner

Anticipated completion: November 2025

June 2025

Project includes:

    • Removal and reconstruction of Field Center in northwest corner of Field Park

Anticipated completion: April 2026

July 2025
Irving School Turf Field

Project includes:

    • Turf field replacement (split cost with Irving School)

Anticipated completion: July 2025

August 2025
Ridgeland Common Recreation Complex

Project includes:

    • Main entrance renovation
    • Rink entrance renovation

Anticipated completion: September 2025

November 2025

Project includes:

    • Geothermal equipment installation

Anticipated completion: May 2026

April 2026

Project includes:

    • Playground renovation
    • Splash pad renovation
    • Field light installation

Anticipated completion: November 2026

April 2026

Project includes:

    • Playground renovation
    • Pickleball court installation
    • Splash pad renovation

Anticipated completion: November 2026