Upcoming Construction Timeline
The following is a tentative schedule of projects at Park District facilities and parks. Projects are subject to change.
September 2024
Project includes:
- Diving well removal
- Installation of slides, lily pad crossing, and current channel
Anticipated completion: June 2025
March 2025
Project includes:
- Geothermal well installation
Anticipated completion: May 2025
April 2025
Project includes:
- Playground renovation
- Shade structures
- Entrance moving to northwest corner
Anticipated completion: November 2025
June 2025
Project includes:
- Removal and reconstruction of Field Center in northwest corner of Field Park
Anticipated completion: April 2026
July 2025
Irving School Turf Field
Project includes:
- Turf field replacement (split cost with Irving School)
Anticipated completion: July 2025
August 2025
Ridgeland Common Recreation Complex
Project includes:
- Main entrance renovation
- Rink entrance renovation
Anticipated completion: September 2025
November 2025
Project includes:
- Geothermal equipment installation
Anticipated completion: May 2026
April 2026
Project includes:
- Playground renovation
- Splash pad renovation
- Field light installation
Anticipated completion: November 2026
April 2026
Project includes:
- Playground renovation
- Pickleball court installation
- Splash pad renovation
Anticipated completion: November 2026