July
South wall nears completion and slab is scheduled to be poured. ComEd has been onsite for electrical installation work.
June
Underground plumbing is complete and underground electrical work is underway.
May
Progress is being made on the rammed earth walls.
April
The first wall passed inspection.
April
A mock wall was built and lettering was approved. Underslab work is to begin soon.
April
Framing for rammed earth is finalized and a mock wall is being built for review.
March
Gravel and sand delivery coming soon. Framing work continues.
March
Wall construction slated to begin mid-March.
February
Framing for rammed earth walls continues.
January
Framing for rammed earth walls is ongoing. Work on the walls will begin in early March. Current work includes pouring the slab and underground work.
January
Backfilled around foundation and added gravel. Roofing details are being discussed.
December
Concrete foundations were poured, and dowels were set.
December
Foundation framing and scaffolding completed.
December
Ongoing work on the composition of the rammed earth walls, including color selection, seal coating, and lettering molds.
November
Foundation walls are being prepared for pouring. Due to pending weather (snow and single digits), the pour has been delayed and will occur once the temps are above freezing and stable.
November
Concrete foundation wall forms are onsite and installation has begun.
November
Column footings have been poured, with foundation wall forming coming soon.
October
Strip footing excavations for east, south, and west walls complete. Rebar placement and forming of strip footings in progress.
October
Forms for the foundation wall were put in.
August
Fencing went up and initial demolition began.