Rehm Diving well Renovations
Rehm Pool is undergoing an exciting transformation! The diving well will be replaced with fun water activities for all ages, including two waterslides, a lily pad crossing, and a current channel. These renovations address structural concerns with the aging diving well.
Check out the latest updates:
Next Up:
Week of March 17: Concrete to be poured for slide footings and pool stairs. Transformer slab and transformer to be installed. Week of March 24: Power to be reestablished in Rehm Park.

March
Roof trusses installed, with roof to be installed the week of March 17.



March
Concrete poured into the pool wall frames. Frames will be removed once concrete sets.


Early March
Pool wall work continues. Check out the new current channel!


February
Pool wall installed amidst snowy conditions.

Early February
Concrete poured on February 4. The team worked hard to beat the incoming rain and ice.

Late January
Gravel compacted and rebar installed.

Early January
Piping under the pool shell completed and inspected.

November-December
Path work done on the new pumphouse building, in addition to laying foundations, footings, and masonry walls.

September
Existing diving well structure removed and the hole filled.