Field Park & Center

Plan Created: 2006
Plan Reviewed: 2024
Next Review: TBD
Construction Completion: Winter 2026

Continued investment in our parks and facilities is critical to the District’s mission. The Park Board’s policy states that each park site plan will be revisited and updated within a 10-year period. The Park District is in the process of revisiting each park site plan per this policy in order to identify additional park amenities desired by our residents, to budget strategically for these improvements and to be prepared for grant opportunities.

If you have questions or would like to provide feedback on park plans currently in progress, contact Bill Hamilton, Superintendent of Parks & Planning. (opens email app)

Timeline Icon

November

Insulation has been installed and is undergoing inspection. The exterior has also been sealed.

pink insulation visible between steel beams on interior of building
Timeline Icon
black lawn material coats playground area

November

Forever Lawn installation began.

Timeline Icon

October

Rooftop insulation complete with shingle work to begin. Interior electrical inspections occurring and ComEd coming to power up the building. Water to be activated as well.

interior of building with steel frames and light wood ceiling
Timeline Icon
playground equipment lies around the construction site

October

Playground installation is underway.

Timeline Icon

October

HVAC and electrical work underway indoors, and interior wall framing complete.

steel beams frame out rooms
Timeline Icon
September
concrete workers spread wet concrete across the floor

September

Timeline Icon

September

Splash pad was poured.

circular concrete area
Timeline Icon
wood roof stretches over rammed earth structure

September

Roofing work is underway.

Timeline Icon

September

Timber posts went up with roofing and slab pour to follow.

large timber beams criss cross the ceiling and into the ground
Timeline Icon
large gravel area covered with rebar

September

At the playground, water and cistern connections underway, along with sidewalk framing.

Timeline Icon

August

Playground demolition is underway.

a large construction excavator works in a gravel area where field playground used to stand
Timeline Icon
Construction of a rammed earth wall at Field Park, with a yellow JCB loader and red Werner ladders present.

August

Rammed earth walls are complete.

Timeline Icon

July

South wall nears completion and slab is scheduled to be poured. ComEd has been onsite for electrical installation work.

Construction of Field Park building with workers and a yellow JCB telehandler.
Timeline Icon
Construction of the Field Park building shows the foundation and framing. Trenches for plumbing are visible.

June

Underground plumbing is complete and underground electrical work is underway.

Timeline Icon

May

Progress is being made on the rammed earth walls.

Construction of a rammed earth wall at Field Park, showing wooden formwork and the layered earth texture.
Timeline Icon
Construction of a rammed earth wall at Field Park, showing wooden formwork, rebar, insulation, and the layered earth.

April

The first wall passed inspection.

Timeline Icon

April

A mock wall was built and lettering was approved. Underslab work is to begin soon.

A white Bobcat S650 skid-steer loader is positioned next to wooden formwork for a concrete structure at the Field Park
Timeline Icon
Construction site with wooden formwork for a concrete structure, a yellow Kaeser air compressor, and a Gar Bro concrete

April

Framing for rammed earth is finalized and a mock wall is being built for review.

Timeline Icon

March

Gravel and sand delivery coming soon. Framing work continues.

Construction workers build concrete forms for a new structure at Field Park.
Timeline Icon
Construction site for Field Park with wooden framing and a red tarp covering materials. The ground is covered in gravel.

March

Wall construction slated to begin mid-March.

Timeline Icon

February

Framing for rammed earth walls continues.

Wooden formwork for concrete foundation walls is erected at the Field Park construction site.
Timeline Icon
Construction worker in overalls inspects plywood formwork for a concrete foundation at Field Park.

January

Framing for rammed earth walls is ongoing. Work on the walls will begin in early March. Current work includes pouring the slab and underground work.

Timeline Icon

January

January
Construction site at Field Park with an excavator digging in the dirt and rebar sticking out of concrete walls.
Backfilled around foundation and added gravel. Roofing details are being discussed.
Timeline Icon
Construction workers pour concrete into forms at the Field Park construction site. Rebar is visible.

December

Concrete foundations were poured, and dowels were set.

Timeline Icon

December

Foundation framing and scaffolding completed.

Field Park construction site with concrete forms and rebar in the snow.
Timeline Icon
A concrete structure with the letters "E" and "M" displayed. The "E" is a white cutout, and the "M" is carved into the

December

Ongoing work on the composition of the rammed earth walls, including color selection, seal coating, and lettering molds.

Timeline Icon

November

Foundation walls are being prepared for pouring. Due to pending weather (snow and single digits), the pour has been delayed and will occur once the temps are above freezing and stable.

Construction site at Field Park with rebar and concrete forms covered in plastic sheeting. A gazebo is visible in the
Timeline Icon
November
Construction workers prepare rebar and concrete forms for the Field Park building foundation.

Concrete foundation wall forms are onsite and installation has begun.

November

Timeline Icon

November

Column footings have been poured, with foundation wall forming coming soon.

Construction site at Field Park showing trenches with concrete footings and rebar, with orange safety fencing in the
Timeline Icon
October
Construction site at Field Park with excavators, trenches, gravel, and portable restrooms.

Check out the latest updates:

Strip footing excavations for east, south, and west walls complete. Rebar placement and forming of strip footings in progress.

October

Timeline Icon

October

Forms for the foundation wall were put in.x

Construction workers and an excavator are on site at Field Park, preparing the foundation for a new building.
Timeline Icon
Construction equipment and materials are present in a park area undergoing landscaping, with orange safety fencing visible.

August

Fencing went up and initial demolition began.

Acquired in 1916, the park is named after children’s author Eugene Field and includes a center originally designed by John S. Van Bergen. The center has been significantly modified over the years. Woodbine Avenue between Berkshire and Division was vacated by the Village in 1960, to expand the park and connect it to the Mann School grounds, creating roughly five acres of total open space.

The Field Park site master plan was completed in May 2006 with School District 97’s cooperation. Improvements began in August 2007 and finished in April 2008, partially funded by a $399,000 Illinois Department of Natural Resources Open Space Lands Acquisition and Development Grant. Upgrades included new playground equipment, bocce court, splash pad, shelter, walkways, expanded baseball and soccer fields, a new vehicular drop-off, irrigation trunk, benches, drinking fountains, bike racks, and extensive landscaping with new trees. In 2007, Field Center received roof repairs and door and lock replacements. A fire alarm upgrade in 2008 enabled constant detection and direct alerts to emergency agencies. In 2010, restrooms were made accessible when staff are absent, and minor repairs were completed. A new exterior accessible restroom was built in 2011. In 2013, irrigation was added to sports fields.

The District reviewed the master plan with the community in 2014. An underground cistern was installed in 2017 to capture and reuse splash pad water for irrigation. In 2018, the playground surface was replaced, and a natural planting area was added.